Date: 4/09/2025 13:28:48
From: wookiemeister
ID: 2312927
Subject: re: Chat September 2025
The estimated cost for the Snowy 2.0 pumped-hydro project is A$12 billion as of late 2023, which is six times the original forecast. This cost includes a projected increase in capacity to 2,200MW and the associated transmission lines, though the total cost including these extra projects could exceed $20 billion.
The project was first estimated to cost around $2 billion.